format_list_bulleted Topic Overview

Procurement Contracts

A contract is an agreement negotiated by two or more parties. It documents the business relationship by confirming the commitments each party is making and helps avoid later misunderstandings.

A procurement contract is a type of contract that documents Stanford’s agreement to purchase goods or services, including $0 transactions, from a non-SU payee (supplier or independent contractor). It sets key business terms (pricing, deliverables, duration) and legal terms (indemnification, data security, intellectual property). 

Because procurement contracts bind the university to financial or other obligations, they must be signed by a designated authority. Administrative Guide Memo 1.9.1: Signature and Financial Approval Authority designates Procurement Services within Stanford Financial Management Services as the authority to sign contracts for the purchase of goods and services.

In general, a purchase requires routing through the procurement contracts process (outlined below) when:

  • The purchase is a service: The complexity of most services raise additional risks to the university that must be addressed with a procurement contract. Refer to the procurement contract types section below for services that generally require a procurement contract.
  • The goods or services will be provided by an independent contractor: Effective January 2025, California’s Freelance Worker Protection Act requires a written contract with independent contractors.
  • The supplier requests a Stanford signature: Whether it is a good or service, including zero dollar ($0) exchanges, if the supplier presents the department with a legally binding document requiring a signature, it must be reviewed, negotiated, and signed by Procurement Services.

Purchases that do not require routing through the procurement contracts process (e.g., common goods such as office supplies) can be acquired through Stanford’s reuse resources or purchased through other methods (e.g., Amazon Business, SmartMart Catalog Suppliers, etc.). 

Contract types that are not considered Procurement Contracts

The following departments process other types of contracts:  

Below are the procurement contract types currently available in the SmartMart Contracts system, along with descriptions and related resources that provide further guidance for using each contract type. Each contract type drives the dynamic contract request form in the SmartMart Contracts system with questions required for the specific type of professional service.

Based on the descriptions below, schools and units should select the contract type in the SmartMart Contracts system that best aligns with the type of professional service the supplier or independent contractor will provide. 

Procurement Contract Types Available in SmartMart ContractsDescriptionRelated Resources
Architecture & EngineeringThe supplier will provide architecture and/or engineering services related to the design and construction or renovation of a Stanford building.Refer to the Construction services section on the Topic Overview: Purchase Services page for more details, including considerations for construction services that are part of a capital project.
Artist, Performer, or SpeakerThe supplier will perform, speak, or provide an intangible performance piece at a Stanford event on a one-time or ongoing basis.Refer to the Speaker (non-Honoraria) section on the Topic Overview: Purchase Services page for more details, including criteria for when honoraria can be paid to speakers.
Artwork, Illustration, or PhotographyThe supplier will provide artwork, illustrations, or photography where Stanford will acquire intellectual property (IP) use or ownership rights.Refer to the Professional Services section on the Topic Overview: Purchase Services to learn about purchasing and payment methods for these types of services.  
CateringThe supplier will provide food (and drinks) for a specific single department event.Refer to the Event Venues and Catering section on the Topic Overview: Purchase Services to also learn about other on-campus venues and services that can be arranged through LBRE’s Event Services and do not require a contract. 
Charter Services (Bus, Plane, or Boat)The supplier will provide bus, plane, or boating charter services.Refer to the Charter Services section on the Topic Overview: Purchase Services for information on the different types of charter services and payment methods.
Chemicals and GasThe supplier is a licensed provider of chemicals and gas services on a one-time or an ongoing basis. Many chemicals and gases are available through SmartMart Catalog Suppliers. If a contract is required for the purchase of chemicals and/or gases that are not available through the catalog, a request should be submitted in SmartMart Contracts.
ConstructionThe supplier is a licensed construction contractor who will build or renovate a campus building.Refer to the Construction services section on the Topic Overview: Purchase Services page for more details, including construction services that are part of a capital project.
Consulting

The contractor is a professional firm (or an individual) with specific subject matter expertise who will provide such expertise in specific tasks, for a specific project, within a specific period of time.

Typically, a Consulting agreement documents how a consultant will advise the university on how to perform the work, while a Technical Services agreement documents the delivery of work on behalf of Stanford (see the Technical Services contract type below). For example, a Technical Services agreement is used for building a website, while a Consulting agreement is used when a consultant advises Stanford on how to improve the website that is being built.

Examples of consulting services could include management and leadership consulting, strategic planning, user experience (UX), user interface (UI), or other software/network/internet consulting.  

See additional guidance about Independent Contractors/ Consultants on this page. 
Hotel/VenueThe supplier will provide room(s) and/or event space for a specific single department event.Refer to the Group Room Blocks section on the Topic Overview: Lodging page for guidance on booking a room block with hotels that have an existing University-Wide Procurement Service Agreement formerly called Master Service Agreement (“MSA”) with Stanford. A contract is required to book a room block with a hotel that does not have an existing MSA with Stanford.
International/Global Services

The contractor will perform the work outside of the United States, including a U.S. based company or individual performing work in a foreign country as an independent contractor.

There are certain tax implications and international regulations for suppliers performing work in a foreign country for a certain amount of time as well as applicable money conversion rates.

Refer to Step 3: Supplier or Visitor Payee Completes Setup on the Topic Overview: Setting Up a New Supplier or Visitor for details on documentation requirements for non-US (international) businesses and independent contractors.
IT Services

A contractor who provides information and communications technology (IT) will provide such services to Stanford.  


IT services include hardware, software, database purchases, licenses, and/or maintenance, including infrastructure-as-a-service (IaaS), platform-as-a-service (PaaS), software-as-a-service (SaaS), and Data Access Agreements (DAA), which are used for purchasing the access to data from a non-Stanford entity.

Lease (Equipment)The supplier of equipment will allow Stanford to use the equipment for a limited time without transferring any ownership rights in the equipment to Stanford.Refer to Topic Overview: Equipment Leases for more information on renting, borrowing, or using equipment such as a medical device, vehicle, or copier.
Lease (Real Estate)A supplier of land, office space, residential space, or industrial building space (Real Estate) will allow Stanford to use the Real Estate for a limited time without transferring any ownership rights in the Real Estate to Stanford.Refer to Topic Overview: Lease or Rent Real Estate for information on renting or controlling property outside of the historic and Stanford Redwood City campuses.
Non-Disclosure Agreement

Also called a Confidentiality Agreement in which the contractor and Stanford agree not to disclose confidential information shared with each other as part of working together.

A non-disclosure agreement (NDA) is typically only required where confidentiality provisions have not been included in a service agreement.

Confidentiality provisions are incorporated into all relevant Stanford service contract templates and a separate NDA is not typically required.
On Campus Café OperatorThis is the ongoing lease for space between Stanford and a supplier, where the supplier will operate their business to provide food and/or beverages within a campus location.All preparers must answer additional data security questions when submitting a contract request with any suppliers who will facilitate credit and/or debit card payment processing on behalf of Stanford, including on-campus café operators.
Technical Services

The contractor will provide a service to Stanford that does not clearly fall into any of the contract types listed in this table. Such service will include specific tasks, for a specific project, within a specific period of time.

A consulting contract type (see contract type above) should be used if the supplier is advising Stanford on how the work is performed, but will not perform the work on behalf of Stanford.

Examples of technical services include web design, recruiting services, and photography/videography services.

Refer to the Professional Services section on the Topic Overview: Purchase Services for other professional services that do not fall into any of the contract types listed in this table.
Statement of Work (SOW)
(For use with MSAs)

This Contract Type within the SmartMart request form is only used when the request is associated with an existing University-Wide Procurement Service Agreement formerly called Master Service Agreement (“MSA”) 

A Statement of Work (SOW) is a document included with all contracts that details the business terms (price, timing, scope, etc.) of the work to be performed by the supplier or independent contractor.  Using this contract type facilitates the collection of the SoW details for a specific project when an MSA is in place.

Preparers should not use this contract type when there is no current, signed MSA available in SmartMart Contracts; or the SOW has additional terms and conditions that alter or exceed the scope of the MSA. Instead, preparers should select the relevant service agreement contract type (e.g., Consulting Services, Technical Services, International/Global Services, etc.) and attach the Statement of Work document to the service agreement contract request.

Refer to the Contract Considerations and Documentation section below for additional MSA considerations.

Refer to How To: Search for an Existing Procurement Contract for step-by-step instructions on searching for all contracts in SmartMart Contracts, including master service agreements.

The procurement contract process includes four stages. When there is a financial commitment involved, the procurement contract process also includes components of the Purchase Order process.

The pre-request includes the following steps:

  1. Conduct a basic outline of scope.
  2. Review the many potential methods to purchase goods and/or services as these options may meet business needs without requiring the setup of a new supplier or independent contractor (IC).  
  3. Review the policies and guidance on how suppliers or ICs are selected at Stanford. In some cases, a formal Request for Proposal (RFP) may be needed.
  4. The supplier or IC (referred to as a non-SU payee) must have an active supplier or IC record in the university’s database. Check if the non-SU payee has an active record in the university’s database. If no record exists, the department must submit a request to set up a new record before a contract request can be made. For suppliers or ICs set up to receive only non-PO contracts, the record should be available in SmartMart Contracts within 24 hours after the request was submitted.
  5. Communicate with the supplier or IC and document the scope and pricing in a statement of work or proposal. 

Departments and schools begin the procurement contract process when they submit the contract request and obtain subsequent financial approval (when the contract will be paid for by a purchase order).

  1. Request the Contract in SmartMart Contracts

    • Submit new and amended procurement contract requests to Procurement Services using SmartMart Contracts. Certain Capital Equipment purchases are an exception, which may need to be initiated by iProcurement Services.
    • Select how the procurement contract will be paid, which can include payment through a purchase order (PO) or PCard for contracts whose total value is $4,999.00 or less (see non-PO contracts section below for more information).
    • Attach a Statement of Work, proposals and/or draft agreements within SmartMart Contracts. A Statement of Work is a legally binding document that outlines and defines the business requirements for a project or service; including scope of the work being provided, project deliverables, timelines, locations, acceptance criteria, and payment terms.  A Statement of Work may be issued as part of a Service Agreement, or under the terms of a Master Agreement.
    • If the department is working with an independent contractor, attach a signed Independent Contractor Checklist (IC Checklist) within SmartMart Contracts.
    • For procurement contracts involving the non-SU payee's use of Stanford data, departments should review additional considerations and attach required documentation, such as a Data Risk Assessment, which helps inform the contract review and negotiation process.
    • Pricing information should be complete and summarized in the contract request form so it can accurately populate the funding information in the iProcurement requisition (see number 2 below). An example of complete and summarized pricing information is: “Consulting fees, estimate of 10 hours at $125.00 per hour for expertise in website design, total Not-to-Exceed (NTE) price of $1,250.00."
    • Once the contract request form is submitted, Procurement Services will review the request form and return the request form with any questions or corrections if needed.
    • If the procurement contract will be paid for by a PO, the preparer will receive an email providing the requisition number, and instructions on how to continue in iProcurement. Non-PO contracts will proceed to Procurement Services review and approval. Once the contract is signed, the payment can be processed. Event venue or catering service deposits can be processed while the contract request is being reviewed.

If the preparer needs to modify the contract request after the preparer has clicked the “Submit Request” button, they must contact the Contracts team using the communications tools available within SmartMart.

Procurement Contract Request Processing Timeframes

Contract request processing times vary depending on the:

  • Complexity of each contract
  • Turnaround time for supplier to respond to questions, review, and sign the contract
  • Volume of other contract requests that Procurement Services is processing at the time the request is submitted.
  • When applicable, reviews needed by other departments (e.g., the Office of General Counsel, Global Business Services, or Office of Technology Licensing) for unique circumstances/risks
  • Use of Stanford data (see contract considerations and documentation section on this page)
  • Peak seasons (e.g., year-end, commencement)

The Contract Advisor assigned to your contract request will process it as quickly as possible based on the above factors. If a rush is needed for the contract request, refer to Step 5 in How To: Submit a Contract Request

Communicating with the Procurement Contracts Team

To ensure proper documentation of all contract discussions with the Contracts team, departments should use the following SmartMart Contracts messaging tools, based on the contract stage:

  • The Discussion tab in the request form when the contract request status is Under Review.
  • The Communications Center in the Contract File, once the contract request status is Accepted, specifically to ask Procurement to:
    • Add stakeholders to who will be able to view the contract file or monitor its status
    • Make edits before signing the contract.
    • Cancel the Contract File and related purchase requisitions/orders.
    • Respond to questions

2. Obtain Financial Approval in iProcurement

Please note: Non-PO contracts will not have financial review and approval in iProcurement.

For procurement contracts that are paid for through a purchase order:

  • After receiving an email with the requisition number, the preparer must log into their “My Requisitions” page in iProcurement and add the PTAE(s )to the purchase requisition. A designated PTAE approver is auto-populated in the requisition based on the PTA and the dollar amount being requested.
  • University policy requires that purchases be by competition to the extent possible based on considerations such as quality, price, and performance. To document competitive purchasing practices, schools and units can attach documentation such as multiple bids or quotes to the non catalog purchase requisition. Procurement Services is required to validate competitive supplier selection over a threshold that is dependent on the funding source.
  • If pricing information (e.g., price per hour, total number of hours, price per deliverable, or lump sum pricing for the total amount of work) is fragmented across the Statement of Work (SOW), proposal, and/or draft agreement, also attach these multiple documents to the non-catalog purchase requisition that was generated from the contract request.
  • Submit the purchase requisition for financial approval. If the contract request contains a monetary value, the funds must be fully approved before the contract signature can be completed. For more information, see Topic Overview: Financial Transaction Approval.

For more details on submitting a purchase requisition with appropriate documentation, refer to Purchase Orders.

Please note: If the preparer needs to cancel a purchase requisition associated with a procurement contract, they must contact the Contracts team using the Communications Center to request cancellation of both the contract file and the purchase requisition.

After the purchase requisition or the non-PO contract request has been approved, the Procurement Services Contracts team will:

  1. Review the contract file
  2. Draft the agreement
  3. Negotiate any changes to legal terms requested by the supplier to ensure alignment with university policy
  4. Request signature from the supplier
  5. Sign the contract on behalf of Stanford

Occasionally, the Contracts Team may need additional review of specific terms or clauses by other departments (e.g., the Office of General Counsel, Global Business Services, or Office of Technology Licensing) that pose unique circumstances/risks, which may affect processing time. If the procurement contract will involve the use of Stanford data by others, please refer to the Use of Stanford Data section on this page. Fiscal year end generally sees a significant increase in the volume of contract requests and can impact processing time.

Execution

If the procurement contract will be paid for by a PO, the PO number is included in the contract prior to signature. The preparer of the contract request will receive a SmartMart Contracts system-generated email letting them know when the contract has been fully signed.

Because the contract governs the transaction, Oracle Financials does not send an automated email to the supplier or preparer with a copy of the PO. A PO file may remain in Oracle Financials for invoice purposes only. After the contract has been signed, the preparer and named contract stakeholders can download a copy of the signed agreement within SmartMart Contracts, if needed.

The table below outlines the description and process for possible actions a preparer can take on a contract that has been fully executed/signed:

Preparer ActionDescription and Process
Request cancellation of the PO associated with the contract (POs with no invoice activity)When a PO associated with a contract has no invoice activity, perhaps because the goods or services will no longer be fulfilled by the supplier or the department no longer requires them, the preparer can contact the Contracts team using the Communications Center to request cancellation of both the contract and PO. Before canceling a contract and the associated PO in Stanford’s financial systems, the department should notify the supplier.  
Upload an invoiceSuppliers typically submit invoices directly to AP for payment. Departments can, at their discretion, require the supplier to submit invoices directly to the department for review and uploading. Accounts Payable processes invoices and schedules payment per the terms specified in the contract (e.g. net 30 days from date on the invoice).
Process PCard PaymentsFor Non-PO contracts, departments should wait until the contract is signed before processing PCard payments. It is acceptable to process refundable deposits on a PCard for contracts related to event venues before the contract is executed. See the Topic Overview: Purchase Services for more information on purchasing event venues and catering services. 
Request Simple Financial Changes to the Active PO

There are several activities that can occur on an active PO, such as a PTA change, which do not impact or involve the supplier or independent contractor and therefore do not require an amendment to the contract.

See the Topic Overview: Purchase Order Process on how to review, access, and manage an active purchase order.

Request a Contract Amendment

An amendment is a legally binding document that records any agreed upon changes to an executed contract

Changes need to go through the amendment process because there is an amendment clause in all Stanford contracts specifying that “agreements shall not be changed, except in writing, signed by both parties.” 

Amendment examples include changes to the:

  • Scope of work
  • Contract start or end date
  • Amount of money being paid to the supplier or independent contractor
  • Requirements due to the law or university policy

Requests to amend a contract are submitted in SmartMart Contracts. See the How To: Amend a Contract for the end-to-end contract amendment process on a contract that is signed and fully executed. 

The amendment request may require attaching an updated Statement of Work or other documentation. If the amendment requires an increase in the amount of money in the contract, then a change order purchase requisition is automatically created in iProcurement, and the requester must complete and submit it for financial approval. 

Financial changes to non-PO contracts that increase the total value of the contract to $5,000 or more must be requested by submitting a new contract request in SmartMart Contracts, which will generate a purchase order in Oracle to accommodate funding outside of the PCard limits.

Request a Contract Extension

A contract extension is a type of amendment to provide additional time to complete the currently contracted scope of work.

Contract extensions are entered in the SmartMart Contracts system as a request to “Amend/Change a Contract.” Refer to How To: Amend a Contract for instructions.

If the contract amendment is only for additional time (and does not require additional money) a purchase requisition will not be automatically created in iProcurement. The amendment will route directly to the Contracts Advisor assigned to the agreement for review and signature.

Request a Contract Renewal

A contract renewal creates a new contract between the parties. Most often, the majority of the new contract is a repeat of the business and legal terms agreed in the prior contract, with the only changes being start and end dates, and the amount of money being paid. Therefore, instead of writing an entirely new contract, a much shorter document is written to confirm that both parties agree to all the same terms of the prior agreement plus the new dates, amount of money, and any other minor changes such as updated contact information.  Please note that after a number of contract renewals, the contracts team may elect to write an entirely new contract rather than trying to track multiple amendments and renewals.

Contract renewals are entered in the SmartMart Contracts system as a request for a “New” contract.

When the renewal requires PO funding, a purchase requisition is automatically created in iProcurement and the requester must complete and submit for financial approval.

Manage Potential Issues or DisputesRefer to the Topic Overview: Managing the Supplier Relationship and Record for more information on how to manage disputes with suppliers or independent contractors when the delivered product or service is not meeting expectations. In some situations, schools and units can request that the Accounts Payable (AP) team place a hold on an invoice associated with the contract, allowing additional time to communicate with the supplier or independent contractor and reach a reasonable resolution.
Request a Contract Termination

Most Stanford contracts automatically terminate at the “end date” set in the contract. The university generally does not allow “evergreen” or automatic contract renewals because they represent a financial risk; creating legal obligations to pay money that has not been budgeted. 

If a department wishes to terminate a contract before the scheduled “end date,” please contact the assigned contract advisor in the SmartMart Contract Communication Center for assistance. See How To: Use Message Tools Within SmartMart Contracts for further information.

The contracts advisor will request a detailed explanation of why the department requests early termination. 

If there is a dispute between the department and the supplier or independent contractor, Procurement Services will require documentation of communications between the department and the supplier or independent contractor that demonstrate efforts to reasonably resolve the dispute.

If a department has reason to believe that Stanford’s relationship with a specific supplier or independent contractor should be terminated on behalf of the entire university community, they should submit a help ticket with details. Procurement will then coordinate with OGC, OCRO, stakeholders, and senior leadership to determine appropriate actions.

If a staff member is aware of conduct that violates, or anticipates a situation that potentially violates, university policies such as the Code of Conduct or Conflict of Commitment and Interest, they should notify the appropriate university officer or reach out to the Ethics & Compliance helpline.

Contracts Submitted Through a Non-Catalog Requisition in iProcurement

For questions on contracts that originated in iProcurement prior to the launch of the new SmartMart Contracts system, please submit a support request.  

Contract requesters can view the status of the contract request and contract file in SmartMart Contracts. The following table provides descriptions of the SmartMart Contracts system statuses.  

Stage of ProcessStatusWho must take actionDefinition
Contract RequestIncompleteRequesterThe Contract Request is in progress by the requester and has not been submitted.
Contract RequestUnder ReviewContracts Intake TeamThe Request is being reviewed by the Contracts Intake Team.
Contract RequestReturnedRequester

The Request was reviewed and returned by the Contracts Intake Team for additional information or instructions.

Please make the needed changes and resubmit the Request by clicking the “Submit Request” button.

Contract RequestAcceptedN/AThe Request was accepted by the Contracts Intake Team and created a Contract File.
Contract FilePending ApprovalDepartment Financial Approver
and/or
Contracts Team

For contracts to be paid via iProcurement, the Contract is waiting for financial approval in Oracle.

For zero dollar ($0) contracts or contracts to be paid via PCard, the Contract is waiting to be processed by the Contracts team.

Contract FileDraftContracts Team
and
Supplier/IC
The Contract is in the creation/review/ negotiation process with the Contracts team and the Supplier/IC’s legal team.
Contract FileInternal ReviewContracts TeamThe Contract is under review with the Contracts team.
Contract FileExternal ReviewStanford 
Policy Stakeholder
The Contract is with a Stanford Policy Stakeholder for review of changes requested by the Supplier/IC.
Contract FilePending SignatureContracts TeamThe Contract is in the e-signature system.
Contract FileOut for SignatureSupplier/ICThe Contract is with the Supplier/IC for their signature.
Contract FileExecuted- FutureN/AThe Contract is signed but the Effective date is in the future.
Contract FileExecuted- In EffectN/AThe Contract is signed by all parties and Effective - the workflow/process is COMPLETED.
Contract FileSupersededN/AThe Contract File has been replaced through an Amendment.
Contract FileTerminatedContracts Team
and
Supplier/IC
The contract has been brought to an end, generally before its expiration date, often due to mutual agreement or specific early termination clauses within the agreement.
Contract FileExpiredN/AThe Contract has passed its end date (completed the term) and was not renewed or extended.
Contract FileCompleteSupplier/ICAll services or deliverables have been provided by the supplier/IC and all payments processed.

A non-Purchase Order Contract (non-PO contract) is a contract that does not require funding approval in Oracle. Non-PO contracts include:

  • Zero dollar ($0) contracts: This type of procurement contract is typically used when a supplier or independent contractor will provide Stanford with goods or services (including access to data) but at zero dollars ($0) paid by Stanford.
  • Contract with a total dollar value of $4,999 or less that will be paid by a Stanford Purchasing Card (PCard):  Procurement contracts paid with a PCard generally include event and catering services or certain professional services. They must comply with PCard policy

Stanford’s Vendor Services team has established a 24-hour process for setting up a supplier or independent contractor who is limited to non-PO contracts, when tax and payment information is not required. Once such a request is submitted through the Supplier Query and Request tool, the supplier or independent contractor will be available in SmartMart Contracts within approximately 24 hours. Such suppliers or independent contractors are solely available for non-PO contracts and not available for payments through a PO or the Expense Requests system (ERS). Departments can request an update to the payee record to make it available for PO payment.

Financial changes to non-PO contracts

If there are financial changes to non-PO contracts that increase the total value of the procurement contract to $5,000 or greater, the supplier or independent contractor record must be updated, and the supplier or independent contractor fully onboarded to allow the submission of PO transactions. A  new contract request in SmartMart Contracts must also be submitted, which will generate a purchase order in Oracle to accommodate funding approval outside of the PCard limits. 

At Stanford, procurement contracts are generally project-specific. Even if a supplier or independent contractor has an existing procurement contract, it cannot be repurposed for a different department or project.

What is a University-Wide Service Agreement

A University-Wide Service Agreement, formerly called a Master Service Agreement (“MSA”) is like an "umbrella agreement." It covers the broad legal terms that apply to future collaborations with the supplier. It sets the overarching rules for legal terms like data security and confidentiality, trademark and other IP rights, and how disputes will be handled.  However, it doesn't define the actual work to be performed, the budget, or any other project specific business details.

Instead, for each distinct project, a separate Statement of Work (SOW) document is created. This is the detailed "project plan." It outlines all the specific business terms for the project, like exact services, deliverables, schedule, and pricing. The SOW then operates under the legal framework established by the MSA. When the department is ready to start a new project with a supplier who has an MSA, a new contract request is submitted in the SmartMart Contract system to formalize the project-specific SOW.

Types of MSAs

The university primarily uses two types of MSAs:

  • Construction: The supplier is a licensed construction contractor who has generally provided services to a number of different departments on a number of different projects for Stanford.
  • Technical: The supplier has subject matter expertise and has generally provided technical and/or consulting services to a number of different departments on a number of different projects for Stanford.
  • Hotel/Venue: Stanford currently has MSAs in place with the Sheraton Palo Alto and the Westin Palo Alto hotels for services. The quote for these two hotels does not require routing through SmartMart Contracts. Instead, the preparer can attach the quote for the services to the purchase requisition and the hotels will accept Stanford’s PO in lieu of a signature on their quote.

When schools or units engage an individual to perform services, Stanford must ensure the person and the work being performed meet the legal requirements for status as an independent contractor (sometimes also called an independent consultant). Refer to Resource: Independent Contractors for more information on requirements for an IC classification and the procurement process for ICs.

Special care must be taken when Stanford data is used or accessible by others. Whether it be consultants who may use the data or services that host it, data risk classification must be considered. See the Data Risk Assessment (DRA) FAQs and Third Party Security Requirements for more information. Procurement contracts with consultants or hosting services will require a DRA review of data risk by the Information Security Office (ISO) and University Privacy Office (UPO). The DRA process could take from four to six weeks, so it is important to start the process early. Complete the Data Risk Assessment (DRA) with the university’s ISO office and attach a copy of the final DRA Report to the SmartMart contract request.

Additional contract terms may need to be incorporated into procurement contracts when the supplier performs a service function or activity that may involve the use, access, transfer, or storage of moderate or high risk data. Please consult Procurement Services through an FSC support request as soon as the purchase has been identified as involving moderate or high risk data, such as data protected by the Health Insurance Portability and Accountability Act of 1996 (HIPAA), or other similar Federal or State security requirements.

HIPAA is a federal law that requires the protection of sensitive patient health information from being disclosed without the patient's consent or knowledge. HIPAA regulates the disclosure of Protected Health Information (PHI) between Stanford and any supplier who performs services that involve access, use, or disclosure of PHI. Generally, PHI is health information, including demographic data that identifies, or could be used to identify, a specific individual related to their past, present, or future physical or mental health, including provision of health care, or the payment of health care.  Identifiers may include name, address, birth date, and Social Security number.

A Business Associate Addendum (BAA) needs to be attached to the procurement contract in the following circumstances. 

  • The school or unit is working with a supplier who will receive, maintain, transmit, or create Stanford PHI for non-treatment purposes, and
  • The supplier does not qualify for an exemption from the HIPAA requirements. If one of the following exemptions is met, a BAA is not required, but other terms may be appropriate for data protection (e.g., Data Use and Data Security provisions). Exemptions include:
    • All data is de-identified
    • Data is part of a payment to a health provider
    • Data is being transferred to a health oversight agency as part of a federal or state program
    • Data is part of a claim sent to a health plan.
    • Data is part of a fund transfer to a financial institution
    • Data is being sent in response to a request from law enforcement or subpoena

The school or unit can obtain additional BAA information from the Purchase Order Terms and Conditions page on Fingate in the Business Associate Addendum (BAA) section

When a supplier facilitates credit and/or debit card payment processing on behalf of Stanford, it means that community members (e.g., students or members of the public) give their card information to suppliers to purchase items from:

  • The university, such as tickets to a Stanford-sponsored concert or sporting event, or 
  • A supplier at a Stanford campus location, such as a campus cafe, vending machine, or web site operated and owned by the supplier, but, where the purchaser might reasonably believe they are making a payment directly to Stanford.

When working with suppliers that will facilitate credit and/or debit card payment processing on behalf of Stanford, contract preparers must ensure compliance with Stanford’s associated policies and align supplier engagements with any additional requirements requested by Merchant Services and the Information Security Office (ISO). This includes:

  • Consult with the Merchant Services team by submitting a support request. After receiving this consultation, attach a copy of the email confirmation from Merchant Services to the SmartMart contract request.
  • Complete the Data Risk Assessment (DRA) with the university’s ISO office and attach a copy of the final DRA Report to the SmartMart contract request.

The university’s standard Contract and Purchase Order language also addresses Payment Card Industry Data Security Standards (PCI-DSS) with suppliers who process credit and/or debit cards on behalf of Stanford. 

Last Updated: Oct 10, 2025